Generated by LogisticsDX Enterprise Solutions James Fischer-Myall · Sign out
4 | Early Risks, Opportunities and Quick Wins
Protect delivery now, and hold the bigger opportunities until the pipeline is complete
Guiding principle: the client didn't want dramatic change. The existing pipeline of mandates gets delivered first. Anything new is added only where it helps that delivery, and strategic change waits until the pipeline is complete. It's tested with the client and adjusted in the first week.
Risks
Change that distracts from delivery. This is the biggest risk I'd bring as a new starter. Mitigation: no
new systems or restructures in 30 days, and Level 2 only where it helps live jobs
A committed job slipping on time, cost or quality. Mitigation: weekly live-jobs check-in and clearing
blockers quickly
Over-committing: new work stretching current crews and plant. Mitigation: capacity check with the general manager before
new commitments
Cash gaps if milestones aren't invoiced promptly. Mitigation: invoice as each milestone is completed
Losing the team's trust by coming across as corporate. Mitigation: listen first, be on site, and help
before suggesting anything
Quick wins
Only things that help the current pipeline, using existing tools:
Level 1 Clear the blockers job leads raise in week one, and let them know it's done
Level 1 Confirm tickets and inductions for everyone on live sites
Level 2 Invoice each milestone as it's completed and follow up overdue debtors weekly
Level 2 Capture variations on live jobs as they happen
Level 2 One short weekly check-in on live jobs, with owners and dates
Opportunities, once the pipeline is delivered
Level 3 Use actual costs from completed jobs to price future quotes more accurately
Level 3 Plan crews and plant ahead of the next pipeline
Level 3 Reduce manual admin, such as supplier invoice processing
Level 3 A simple KPI pack built from existing systems
Level 3 Grow recurring maintenance work off the back of completed jobs
Put forward at day 30. The owner and general manager decide the timing.
Examples of the later opportunities
To show how I'd approach the Level 3 opportunities, I put together three small prototypes on
invented data. They aren't proposals for the 30-day engagement. They're examples of what could be considered once the
committed pipeline is delivered, if the owner and general manager want to go down that path.